Do You Need Help With An Erection?
Commercial Scaffold Erection Southampton – Brunswick Gate
Main Building Perimeter, including rear West Elevation. (Review 1, Phase 2).
For this Commercial Scaffolding project, We erected an independent scaffold to the South, West & East elevations of the building to give access for major refurbishment works and extension of the existing building up another floor.
In total, the scaffold was approximately 125 metres lineal x 15 metres high to roof level, which extended to 17 metres high when the additional floor was installed.
At a high level, we needed to bridge over 2 no. adjacent properties to achieve full access.
We also bridged over the rear elevation site entrance. The Independent scaffold was erected in 2 metres fully boarded platforms with double handrail & ladder access to every elevation. The structure was tied to the existing building using Hilti ties fixed to the wall at a ratio of every 16 square metres. The scaffold was also encapsulated with Monarflex sheeting from the 1st / 2nd level up.
This project was erected in compliance with TG20.13.
On the East elevation Street elevation, we installed a 500 kg Platform Hoist for accessing steel and plant onto the roof, plus incorporated a System type Staircase for pedestrian access to the roof without using the scaffold.
Whilst on-site, other works were in operation, so we also installed double handrail edge protection on-site wherever and whenever instructed.
SITE SURVEY CARRIED OUT BY. Mick Johnson 11 / 12 / 20
DUTIES OF ERECTOR.
All operatives were deemed competent as defined by C.I.S.R.S / NVQ Qualification.
INSPECTION OF SCAFFOLD.
When completed, scaffolds were left in a condition suitable to perform the duty for which they are intended. The scaffold was then inspected by a competent person representing SAS Ltd. When found suitable, a Hand Over Certificate was issued.
Personal Protective Equipment.
- Wearing gloves was considered an absolute minimum.
- Where RPE is prescribed, the user was face fit tested.
- Re-useable PPE was thoroughly cleaned after use and not shared with other operatives.
- Single-use PPE was disposed of at the end of each shift.
Project Details
DATE
December 2020
CLIENT
CUSTOMER / LOCATION
Brunswick Gate Southampton
PROJECT TYPE
CONTRACTOR
Superior Access Scaffolding Ltd









